How Can MEP Coordination Support Help Clear Backlogs Without New Hires?

Author: Gsource Technologies

External MEP coordination support can help contractors manage peak workloads without immediately expanding permanent staffing.

Picture an MEP contractor with two in-house coordinators and four active projects. By the second week of the month, 140 clashes are open across the four jobs. Then the architect reissues the plans for one building, and 25 more appear overnight.Hiring a third coordinator would take about two months, and the clash list was growing every day. The contractor decided against it. One project went to external MEP coordination support instead, and the decisions and approvals stayed in-house.

Where the backlog came from

Nothing dramatic caused it. All four projects had model reviews due in the same two weeks. Trade models showed up on different days, and every design revision piled new clashes on top of the old ones. The two coordinators knew each job inside out, and that still didn’t give them more hours. Clash resolution slowed down and the coordinated drawings went out late.

Hiring was an option. The workload, though, had a peak and then a dip, which is a hard thing to put a permanent salary against.

Adding capacity without adding headcount

The outside team took the project with the most open clashes, 70 of them. They merged the trade models, worked through the clashes and kept the issue log current, and issued the updated models, drawings and reports. Back in the office, the two coordinators returned to design decisions, client calls and the clashes that needed an engineer in the room. Here it covered a single project.

Keeping coordination under control

Before the outside team opened a model, the two firms wrote down the scope, the Revit standards and which model revision to work from. Reviews were set for every Thursday, with delivery dates fixed on the same page. Each clash had one name next to it, so none could fall between the two teams.

Nothing went to the field until the contractor’s coordinator had opened the updated models and checked them. Every change still needed an engineer’s approval, and the contractor stayed in charge of the project.

If a backlog is starting to threaten a milestone,MEP coordination services can take on clash resolution and the coordinated models, drawings and reports.

Final takeaway

In the example, all 165 clashes got worked down, and nobody was hired. The contractor kept the decisions and the quality.